Premium Roofing Ltd · Job 5512

Crozier Road Re-Roof

4175 Crozier Road, Armstrong BC · Woodtone Specialties Inc. · Full replacement, six roof areas, IKO Innovi 80 mil TPO induction welded.

Position as at 8 September 2026 · audited
Contract $1,742,988
Client contact Edwin Zeller
Contract value
$1,742,988
$1,717,988 base + $25,000 CO
Invoiced to date
$892,462
five invoices, incl. GST
Outstanding — per AR export
$198,256
Inv 15269 · Section C final, 100% · 4 Sept
Margin, work complete
37.7%
B + C on direct cost · 36% with start-up spread
Roof area
81,858
sq ft across six sections
Credits in play
+$14,701
net · two claims in, one credit out
Variables
+$12,485
priced upside · 5 COs open · exposures below

Credits in play

Super Save — Section C rate correctionFive invoices at $339/t that should be $55. Not yet lodged. B precedent on file.
+12,864
Dekfast return — 13 boxes to PacificUnused, with Lane. Ask for restocking to be waived.
+6,037
Sheathing credit owed to Woodtone65-sheet East building allowance, none used. Rate is a Matt question.
−4,200
Net credits in play
+14,701

Variables — not in the contract yet

Three new skylights, Section FEstimate. CO to draft once Edwin confirms location.
+10,635
Damaged skylight, West buildingMay be the one already in the quote. Checking with Lane and Dare.
to confirm
GST gaps — netting CO and insuranceNeeds a closing invoice and an accountant’s answer.
+1,850
Netting moves · sleepers · parapet build-up · extra drainFour change orders with no price yet.
to price
Section F disposal if the rate is not fixedAgainst a $10,800 dump-fee allowance.
−18k to 25k
Dekfast balance if the order is not cancelled60 plate boxes, 31 fastener boxes still on order.
−41,498
Priced upside · downside if nothing is actioned
+12,485 · −60k to 66k

Where the job is

Schematic · areas from the winduplift drawing · not to scale
WEST BUILDING EAST BUILDING A NOT IN CONTRACT B 9,680 SF COMPLETE · BILLED C 16,440 SF COMPLETE · BILLED K 5,330 SF NOT STARTED D 5,248 SF HALF RIPPED E 10,540 SF NOT STARTED F 34,620 SF · 42% of the job NOT STARTED · 26 EXISTING SKYLIGHTS 606 LF PERIMETER · 600 LF CURB G / H / I — future divisions, not in this contract
Complete and billed In progress Not started

What needs attention

Ordered by what it costs to leave alone

Super Save is billing tear-off as "Dirt" at $339 a tonne

Section B was chased and credited — Super Save reversed all three invoices on 31 August and re-billed at $55.00 a tonne, dropped the war fuel premium and cut the fuel surcharge to 14%. Section C has not been chased: five invoices, 38,810 kg, $13,157 charged against $2,135 correct. They were already applying $55 to other C loads in the same weeks.

Invoices 8994949-0 · 9020337-0 · 9025085-0 · 9024883-0 · 9023391-0
+$12,864

Section F disposal only works at the corrected rate

Matt budgeted $19,800 for F — twenty bins plus three dump fees. At 34,620 SF, F should generate roughly 105 tonnes: about $5,800 at $55 a tonne, up to about $35,600 if it all went at $339. Section C ran about three quarters of its weight at the high rate, so the realistic exposure is $18,000 to $25,000 against a $10,800 dump-fee allowance. Fix the waste classification before East building tear-off ramps up.

East building Section F · avoided overrun
−$18–25k

The Dekfast order was never cancelled

Dekfast ordered 15 July on invoice 58275200; the same quantities re-ordered as IKO product on 20 July, invoice 58279696. The IKO order looks like the correction — but the Dekfast line was never closed and still has 60 plate boxes and 31 fastener boxes to ship. None of it went into the roof, so all 13 delivered boxes come back unused and there is no warranty question. Return is $5,642; the number that matters is the balance.

Open · Lane · Pacific Roof Centre PO 5512
−$41,498

Two GST gaps — but not the one I flagged earlier

The deposit GST is fine. Each progress invoice reverses that area’s deposit share as out-of-scope and bills the gross value with GST, so Section B carried the full $10,714 and Section C $18,881.50. Nothing lost. Two real gaps remain. The netting change order was invoiced in full on 15211 as a “deposit” with no GST and nothing is scheduled to follow it, so $1,250 goes uncharged unless a closing invoice reverses and re-bills it. And the insurance upgrade was billed GST-free, where the signed quote’s final price of $1,803,887.40 includes GST on it — a $600 difference.

Invoice 15211 · insurance upgrade
+$1,850

Equipment has no budget — it is spending the contingency

The cost report's "Equipment rental" budget is Matt's contingency to the cent, section by section. The real $20,000 scaffolding line lives only on the summary tab that produced the contract price, and never reached the cost report. Equipment has already spent $36,228 against the $31,838 that is actually contingency — before East building scaffold, the roof cutter for two to three months, and generators.

Rebuild the budget from the summary tab
−$4,390

Two completion dates are in circulation, six weeks apart

The schedule Woodtone holds finishes Section F on 31 October with close-out by 20 November. Matt's own model finishes F on 8 December and K on 18 December, with final payment 1 January 2027. His model has tracked accurately — it called B complete 5 August and C on 11 September when C actually finished ten days early. The signed quote says plainly: "We did not allow for work during winter conditions."

Raise with Edwin now, not in November
Winter risk

Time is tracked at a zero cost rate

The labour underrun is real, not a posting gap — 450.9 hours on Section B and 926.5 on C, which against posted cost works out at $71.03 and $63.29 an hour, right on Matt’s $63.75 basis. The crew simply worked fewer hours than the budget assumed. But every time entry carries a cost rate of zero, is marked non-billable, and is coded to “Sales”. The timesheet is a record of hours only, so any change order priced on crew time — netting moves, parapet build-up, skylight curbs — has to be reconstructed by hand. Set employee cost rates and fix the service coding.

QuickBooks Time · blocks CO substantiation
1,419 hrs

Parapets are being built up on Section D — unbilled

Ludovic, 8 September: the new assembly is taller than what came off, so the upstand has to be raised. Scope covers DensDeck at parapets and cap flashing as a separate item — not building them up. Log linear feet, lumber and hours now. If it repeats across the East building that is roughly 1,213 LF by the winduplift drawing: D 292, E 168, F 606, K 147. Matt’s costing carries different figures — D 250, F 705 — so measure on site rather than pricing off either drawing.

Quantify tonight · CO candidate
To price

The welder is a capital asset sitting in job cost

A Varimat 500, non-returnable, charged whole to 5512. It will outlive this job, and on its own it is two thirds of the contingency.

Put to the accountant
$21,260

Questions, by who can answer them

Nothing here is in a document I hold

Darren — financial controller

D1
Has Woodtone paid invoice 15269?Section C final, $198,255.75, dated 4 Sept. The AR export shows it open; it may just be stale.
$198,256
D2
Code the netting to job 5512.Two Amazon orders, 7 Aug: 701-6866091-1759450 (8 tarps, $2,849.20 landed) and 701-0881064-4500217 (220 cables, $1,049.40 landed). Business MasterCard 8116. Nothing in QuickBooks yet. Is the GST inside the import fees claimable?
$3,899
D3
Recode the two Silver Star lines off 5512.ASG bills 1274 ($280) and 1275 ($100). Different job.
$380
D4
Has the Section C Super Save claim been lodged?Five invoices at $339/tonne that should be $55. The Section B credits are the precedent.
$12,864
D5
The tax invoice on the netting — when does the GST on the $25,000 get charged?Invoice 15211 billed CO 5512-3 whole as a “deposit” with no GST line. The sections each get a follow-up invoice that reverses the deposit and charges GST on the gross; the netting has nothing scheduled behind it. Without a closing invoice, $1,250 is never billed.
$1,250
D6
Should the $12,000 insurance upgrade carry GST?The quote’s final price includes it; invoice 15091 did not.
$600
D7
Set employee cost rates in QuickBooks Time.Every entry is at $0 and coded to “Sales”. Until fixed, no change order can be substantiated from the timesheet.
1,419 hrs
D8
Does the $20,000 scaffolding budget exist in the cost report?It is on the summary tab that produced the contract price. The “Equipment rental” line in the report is actually Matt’s contingency.
$20,000
D9
Should the Varimat welder be capitalised?$21,259.56, non-returnable, charged whole to this job.
$21,260

Lane — foreman, East building

L1
Return the 13 Dekfast boxes to Pacific and get the balance cancelled.8 Isoweld plate, 4 #14 4in, 1 #14 2in. Confirmed none went in. The cancellation is the $41,498 part.
$6,037 credit
L2
How many netting moves do you expect across D, E, F and K, and how many crew hours per move?That is the whole East building netting CO. Eight tarps on hand.
CO input
L3
Log every netting install and dismantle in the register.Date, section, square feet, hours. It becomes the CO exhibit.
Ongoing
L4
The damaged West building skylight — is it the one the contract already covers?With Dare. Decides whether it is nil or a $2,700 CO, and whether the three new ones keep their offset.
$2,700

Dare — estimator

A1
What was the single $2,700 skylight in the quote meant to cover?If it was a placeholder for a damaged-on-removal unit, the West building one consumes it. If it was for something specific, the damaged one is a fresh CO.
$2,700

Ludo — foreman

U1
The extra Section C drain — is it the fourth new drain or the fifth?The contract allows four. The close-out list already names four.
Count
U2
Section D parapet build-up — linear feet, lumber, hours. Does it repeat on E, F and K?Not in scope. The drawings disagree on parapet length, so measure it.
To price
U3
Get the photos into CompanyCam.Phone is full and documentation has stopped. It is the evidence for every claim above.
Today

Edwin — Woodtone

E1
Mark the three new skylight locations on the roof plan and confirm they clear the central air ducting.His own note on the signed quote. Section F, over the offices. Do not order until confirmed.
~$10,635
E2
Approve the extra Section C drain.Matt’s ok was internal. No client approval exists.
Unpriced
E3
The schedule conversation.Matt’s model finishes in December; the schedule Woodtone holds says October. The quote excludes winter work.
Winter

Matt — previous project manager

M1
What credit rate was intended for unused East building sheathing?65-sheet allowance across D, E, F and K, none used yet. The contract promises a credit but sets no price. Cost was $49, budget $52.
~$4,200

Pacific Roof Centre

P1
Price and lead time on the 4×8 Special Order Commercial Columbia dome, black frame.My $1,760 is back-calculated. The contract rate was “subject to change if tariffs are applied.” Lead time is what constrains Section F.
Est.
P2
Open-order report against PO 5512.Per-invoice remaining figures restate the standing quantity, so they are indicative. The East building is about to draw hard.
Report

Schedule of values

Billed per the AR invoices · costs from QuickBooks via the controller
SecBuildingArea SFContractBilled Cost actualCost budgetVarianceStatus
BWest9,680214,280214,280148,554157,619−9,065Complete
CWest16,440377,630377,630220,426267,861−47,435Complete
DEast5,248119,23025,03830,407237,235In progress
EEast10,540211,37044,388Not started
FEast34,620562,100118,0411,123406,094Not started
KEast5,330127,90026,85943686,435Not started
Sections81,8581,612,510806,236400,9461,155,244

The “Billed” column for D, E, F and K is the 20% deposit as it was actually invoiced — 20% of each area’s GST-inclusive value, which is what invoice 15091 charged and what each progress invoice reverses. D and E are combined in Connect, so their cost is reported together; they remain separate lines on the schedule of values at $119,230 and $211,370. Start-up carries a further $28,804 of cost against no budget at all — the two Silver Star consulting lines, $380, are a different job and come off 5512.

Invoiced against contract, by section

B
100% · 214,280
C
100% · 377,630
D
20% · 25,038
E
20% · 44,388
F
20% · 118,041
K
20% · 26,859

The West building is closed out. Every East building section sits at the 20% deposit. The deposit was charged as 20% of each section’s GST-inclusive value, which is why the dollar figure — $25,038 on Section D — is a little over 20% of the net contract figure in the table. Same basis the invoices use.

Invoices raised

Five to date · one unpaid
InvoiceDateWhatNetGSTTotalStatus
1509123 JunDeposit — 20% of quote and upgrades, insurance at 100%370,257370,257.48Paid
152117 AugCO 5512-3 debris netting, billed in full as a deposit25,00025,000.00Paid
1521010 AugSection B 100% — 214,280 less 44,999 deposit169,28110,714.00179,995.20Paid
1523719 AugSection C 50% — 188,815 less 79,302 deposit109,5139,440.75118,953.45Paid
152694 SeptSection C 100%188,8159,440.75198,255.75Outstanding
Total862,86629,595.50892,461.88

Received to date $694,206.13. Invoice 15269 is the only one open — terms are due on receipt and it is dated 4 September, so it is already payable. Woodtone has paid every prior invoice on issue, so this is a follow-up rather than a concern.

The deposit mechanism works cleanly: each progress invoice reverses that area’s deposit share as out-of-scope, then bills the gross section value with GST on top. That is why Section B carried the full $10,714 of GST on $214,280 rather than on the net. The netting change order is the exception — invoiced whole as a deposit with no GST and nothing scheduled behind it.

Still to bill

Milestones from the billing plan · net of GST
ItemContractBilledAt 50%At 75%At 100%Left to bill
B214,280214,2800
C377,630377,6300
D119,23025,03834,57759,61594,192
E211,37044,38861,297105,685166,982
F562,100118,041163,009140,525140,525444,059
K127,90026,85937,09163,950101,041
Upgrades105,47831,63073,84873,848
Netting CO25,00025,0000
Total1,742,988862,866295,974140,525443,623880,122

$880,122 net still to invoice, plus GST — a little over half the contract. Section F alone is $444,059 of it, and it is the only section with a 75% milestone, so it bills in three tranches rather than two. The upgrades tail of $73,848 — parapet caps, the warranty and the skylight — falls at completion, which puts it in the same window as the close-out.

The billing plan has the netting change order due at 100% completion. It was actually invoiced up front as a deposit on 15211, which is why no GST was charged and why nothing remains scheduled against it.

Where the completed sections landed

West building B and C · the only sections with meaningful actuals

Section B · complete

Direct labour
32,027 −24,673
Materials and supplies
99,546 +13,133
Disposal
8,283 +2,783
Equipment
8,697 +1,192
Consulting
0 −1,500
Actual against $157,619
148,554

Disposal here is already net of $6,761 of Super Save credits chased down using Matt's information. Without them B would have been $15,044.

Section C · complete

Direct labour
58,634 −43,426
Materials and supplies
138,634 −11,034
Disposal
20,243 +12,143
Equipment
1,123 −5,410
Consulting
1,792 +292
Actual against $267,861
220,426

Disposal is the whole overrun, and the recovery claim is worth more than the overrun. Chase it and C moves from $47,435 favourable to roughly $60,000.

Change order register

One approved · six to raise
5512-3
Debris netting — West building Section C Approved by Edwin Zeller, 5 August. Invoiced in full on 15211, 7 August, paid. The netting was never installed on Section C — material behind the CO is eight tarps and 220 cables, $3,899 landed. Lane put it up on East building Section D on 8 September. The description and the work do not match; square it before the next claim goes to ASG.
$25,000
5512-4
Debris netting — East building, labour to move To draft 5512-3 says in writing that the East building would be priced separately. The netting is moved to each tear-off area rather than consumed, so there is nothing to buy — this is labour to hang, dismantle and re-hang, section after section. Price on moves at $63.75 a man-hour plus contingency and markup. Needs Lane’s estimate of moves across D, E, F and K.
To price
Three new skylights over the offices To draft Edwin's own note on the page he signed. New openings in Section F — cut deck, frame headers, build curbs, tie in. Three at an estimated $4,445 each — the dome cost is back-calculated from the contract rate, not quoted — less the one already in the quote. Do not order until he confirms location and clearance past the central air ducting. Add $1,500–3,000 if the openings cross trusses.
$10,635
Damaged skylight — West building To confirm One unit could not go back on; frame and dome damaged, curb capped with plywood and TPO. May be the single skylight already in the contract rather than a new CO — Silas is checking with Lane and Dare. If it is, the three new skylights lose their $2,700 offset and that CO becomes $13,335.
$2,700 or nil
Three 12" TPO-covered sleepers — Section D To draft New scope, not in the December quote. Price on Matt's rates: $3,060 a day crew, 30% markup, 2.5% contingency, 7% PST.
To price
Parapet build-up — East building To draft Raising the upstand to match the new assembly height. Started on Section D 8 September. Not in scope. Needs linear feet, lumber and hours from site.
To price
Additional roof drain — Section C Confirm first Pooling for more than 72 hours. Approved verbally by Matt Badura — but ASG is Premium's own project manager, not the owner's representative, so this has no client approval. The contract allows up to four new drains and the close-out list already names four.
Unpriced

Open workstreams

Skylights

Existing units, Section C
18
Existing units, Section F
26
In the contract, at $2,700 each
1
Invoiced so far (deposit, inv 15091)
$567
Spent so far
$99.51

Every West building skylight went back on reused. No new unit has been installed yet — which is why no dome appears on any Pacific invoice, only screws and shingle nails. The one damaged unit is still waiting on its replacement — whether that is the contract’s one skylight or a separate $2,700 CO is being checked with Lane and Dare. Forward risk: Section F has 26 units to come off; the West building lost one of 18, so budget one or two more at $2,700, not three.

Sheathing and the Woodtone credit

Delivered — West building B and C
840 sheets
Planned for B and C
842 sheets
Unit price against $52 budget
$49.00
East building allowance
65 sheets
Drawn from it
0

Two sheets under plan on a full replacement of two sections. The contract gives Woodtone a credit for unused sheets and the whole 65 is still live — about $4,200 if credited near the sell rate, which the contract does not actually specify. Section D needed no deck at all. Agree the credit rate with Edwin before close-out, not after.

Netting

The mill runs while the roof comes off. Netting hangs under the deck to stop tear-off debris dropping onto a live production floor, and it moves with the work rather than staying put — so it is a reusable asset, not a consumable. Eight tarps and 220 cables, bought in two Amazon orders on 7 August on the business MasterCard, and none of it is coded to the job yet.

Owned — eight 12′ × 50′ mesh tarps
4,800 SF
Installed — Section D vents, one tarp
600 SF
Safety cables with carabiners
220
Landed cost, two Amazon orders, 7 Aug
$3,898.60
Recorded against job 5512
$0

Material is $3,899 landed — $3,424 of goods plus $475 of net import fees — against a $25,000 change order. The CO was always labour and risk. Which means the East building change order is labour, not material — hanging, dismantling and re-hanging, section after section. 5512-3 already carries “dismantle and move netting as work progresses”, but it is scoped to West building Section C, so every East building move sits outside it and outside the $25,000. Nobody has been counting the moves; the register now does.

Two things ride on this. Woodtone supplies the man lift and the spotters under 5512-3 — if either is missing when the crew needs to shift nets, tear-off stops, and that is a delay record worth keeping. And netting is explicitly not a fall protection device: roof-level debris mitigation still has to be maintained regardless.

Materials — Pacific Roof Centre

Fifteen invoices, 15 Jul – 2 Sep
$242,251
PST
$12,935
ISO 3" remaining of 2,700
~1,850
TPO rolls remaining of 96
~64
MVP remaining of 304
~214
Adhesive remaining of 26
~17

The whole job was released as one order on PO 5512 and is being drawn down — Section F's material is already bought. Crane is billing $750 a lift against a $250 budget, with HIAB hourly on top. Not yet an overrun; the rates are well off.

Two schedules

The one Woodtone holds, against the one Matt costed to
B
7 Aug / 5 Aug
C
18 Sep / 11 Sep
D
30 Jul / 23 Sep
E
21 Aug / 19 Oct
K
4 Sep / 18 Dec
F
31 Oct / 8 Dec

Revised schedule issued to Woodtone, 21 July Matt's costing model
Bars run from a common 15 July start to each section's completion date. Right-hand figures are the two completion dates. Matt's model has tracked accurately so far, and it puts final payment at 1 January 2027.

Sections D and E were scheduled for late July on the client's copy and have only started now — the East building is running roughly six weeks behind that document. The quote excludes winter work, so if the December dates are closer to the truth, Edwin needs telling.